Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management

Received: 29 July 2022     Accepted: 23 August 2022     Published: 29 August 2022
Views:       Downloads:
Abstract

Prefabricated building is a new type of building structure, that is, the residential building is built by industrial production mode. It is a building built by prefabricating some or all components of the building in the factory, then transporting them to the construction site, and assembling the components through special machinery. From the perspective of EPC general contracting mode, this paper discusses the importance of multi line front integration to prefabricated buildings; The integration of design and construction of assembly integrated building is proposed; In combination with the actual engineering cases, the problems often encountered in the construction implementation process are integrated in the early design by considering the safety of the structure, the convenience of construction and the feasibility of bidding and procurement through the early design; This paper summarizes the countermeasures to the common problems in the construction of prefabricated buildings; Put forward the informatization 5D idea with high integration of BIM design and construction. Practice has proved that the integration of assembly integrated architectural design and construction can better control the high integration of project design, construction, information communication and product quality, accelerate the construction progress of the project, and ensure the physical quality of the project.

Published in Science Discovery (Volume 10, Issue 4)
DOI 10.11648/j.sd.20221004.20
Page(s) 270-278
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2022. Published by Science Publishing Group

Keywords

Prefabricated Buildings, EPC General Contracting Mode Perspective, Design and Construction Integration, BIM-5D Technology

References
[1] 柯妍. EPC项目建设全过程工程造价管理研究[D].长春工程学院,2021。
[2] 梁献超.EPC模式下装配式建筑工程质量管理体系与策略[J].建筑经济,2020,41(11):73-78。
[3] 刘姣姣. 大型工程项目一体化管理模式下PMC选择研究[D].重庆大学,2011。
[4] 李颖.工程建设一体化管理模式浅析[J].科技与企业,2016(03):64+66。
[5] 陈兆荣,蔡志立,曾常洛,白忠奎,杜仕帅. 基于绿色建筑的隔震技术在预制装配式结构中的研究应用[A]. 上海来溪会务服务有限公司.2021第五届土木工程国际会议论文集[C].上海来溪会务服务有限公司:上海来溪会务服务有限公司,2022:72-77。
[6] 陈兆荣,蔡志立,白忠奎,赵祯. 高层建筑转换层梁-柱工作机理研究[A]. 上海来溪会务服务有限公司.2021第五届土木工程国际会议论文集[C].上海来溪会务服务有限公司:上海来溪会务服务有限公司,2022:45-51。
[7] 郭水平,陈兆荣. 无人船基地项目结构设计的若干问题[J]. 建筑结构,2022,52(S1):286-292。
[8] 陈兆荣,蔡志立,白忠奎. 高层建筑转换层满跨墙下梁柱受力性能研究及工程案例[J]. 建筑结构,2021,51(S2):122-128。
[9] 杨仁孟,陈兆荣,王森,魏琏. 高层建筑结构在竖向荷载作用下楼板面内应力分析和工程实例[J]. 建筑结构,2017,47(01):17-22。
[10] 魏琏,王森,曾庆立,陈兆荣. 一向少墙的高层钢筋混凝土结构的结构体系研究[J]. 建筑结构,2017,47(01):23-27。
[11] 魏琏,王森,陈兆荣,曾庆立,杨仁孟. 高层建筑结构在水平荷载作用下楼板应力分析与设计[J]. 建筑结构,2017,47(01):10-16。
[12] 赵挺生,胡俊杰,师玉栋,姜雯茜.塔吊安装与拆卸作业安全性分析[J].中国安全科学学报,2021,31(10):32-38。
[13] 陈兆荣,罗盛宗,潘东辉. 底层大空间-单跨框架学校建筑的抗震加固分析与设计[J]. 建筑结构,2016,46(09):90-94。
[14] 郭材林. 建筑铝合金模板施工质量控制[D].湖北工业大学,2017。
[15] 张韩,梁勇,刘磊,戴锦阳.BIM技术在装配式建筑中的应用[J].华北理工大学学报(自然科学版),2021,43(01):86-93。
[16] 陈戊荣,陈兆荣,苏运升,李雯琪,尹烨,李若羽. 超短临时建筑核酸检测实验室设计若干技术研究[J]. 建筑结构,2022,52(S1):704-708。
[17] 陈戊荣,陈兆荣,苏运升,李雯琪,尹烨,温丽娟,李若羽,陈唯军. 气膜性建筑结构核酸检测实验室的创新设计研究[J]. 建筑结构,2022,52(S1):698-703。
[18] Chen Wurong, Su Yunsheng, Chen Zhaorong, Li Wenqi, Yin Ye, Wen Lijuan, Li Ruoyu, Chen Weijun. Innovative Practice of Key Technologies in Nucleic Acid Detection Laboratory of Gas Membrane Building Structure [J]. Science Discovery, 2022, 10 (1).
Cite This Article
  • APA Style

    Cai Zhili, Zhang Jichao, Chen Zhaorong, Chen Wurong, Ke Biaozhi, et al. (2022). Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management. Science Discovery, 10(4), 270-278. https://doi.org/10.11648/j.sd.20221004.20

    Copy | Download

    ACS Style

    Cai Zhili; Zhang Jichao; Chen Zhaorong; Chen Wurong; Ke Biaozhi, et al. Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management. Sci. Discov. 2022, 10(4), 270-278. doi: 10.11648/j.sd.20221004.20

    Copy | Download

    AMA Style

    Cai Zhili, Zhang Jichao, Chen Zhaorong, Chen Wurong, Ke Biaozhi, et al. Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management. Sci Discov. 2022;10(4):270-278. doi: 10.11648/j.sd.20221004.20

    Copy | Download

  • @article{10.11648/j.sd.20221004.20,
      author = {Cai Zhili and Zhang Jichao and Chen Zhaorong and Chen Wurong and Ke Biaozhi and Zeng Changluo},
      title = {Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management},
      journal = {Science Discovery},
      volume = {10},
      number = {4},
      pages = {270-278},
      doi = {10.11648/j.sd.20221004.20},
      url = {https://doi.org/10.11648/j.sd.20221004.20},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.sd.20221004.20},
      abstract = {Prefabricated building is a new type of building structure, that is, the residential building is built by industrial production mode. It is a building built by prefabricating some or all components of the building in the factory, then transporting them to the construction site, and assembling the components through special machinery. From the perspective of EPC general contracting mode, this paper discusses the importance of multi line front integration to prefabricated buildings; The integration of design and construction of assembly integrated building is proposed; In combination with the actual engineering cases, the problems often encountered in the construction implementation process are integrated in the early design by considering the safety of the structure, the convenience of construction and the feasibility of bidding and procurement through the early design; This paper summarizes the countermeasures to the common problems in the construction of prefabricated buildings; Put forward the informatization 5D idea with high integration of BIM design and construction. Practice has proved that the integration of assembly integrated architectural design and construction can better control the high integration of project design, construction, information communication and product quality, accelerate the construction progress of the project, and ensure the physical quality of the project.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Exploration on the Integration of Integrated Design and Construction of Prefabricated Assembly from the Perspective of EPC Management
    AU  - Cai Zhili
    AU  - Zhang Jichao
    AU  - Chen Zhaorong
    AU  - Chen Wurong
    AU  - Ke Biaozhi
    AU  - Zeng Changluo
    Y1  - 2022/08/29
    PY  - 2022
    N1  - https://doi.org/10.11648/j.sd.20221004.20
    DO  - 10.11648/j.sd.20221004.20
    T2  - Science Discovery
    JF  - Science Discovery
    JO  - Science Discovery
    SP  - 270
    EP  - 278
    PB  - Science Publishing Group
    SN  - 2331-0650
    UR  - https://doi.org/10.11648/j.sd.20221004.20
    AB  - Prefabricated building is a new type of building structure, that is, the residential building is built by industrial production mode. It is a building built by prefabricating some or all components of the building in the factory, then transporting them to the construction site, and assembling the components through special machinery. From the perspective of EPC general contracting mode, this paper discusses the importance of multi line front integration to prefabricated buildings; The integration of design and construction of assembly integrated building is proposed; In combination with the actual engineering cases, the problems often encountered in the construction implementation process are integrated in the early design by considering the safety of the structure, the convenience of construction and the feasibility of bidding and procurement through the early design; This paper summarizes the countermeasures to the common problems in the construction of prefabricated buildings; Put forward the informatization 5D idea with high integration of BIM design and construction. Practice has proved that the integration of assembly integrated architectural design and construction can better control the high integration of project design, construction, information communication and product quality, accelerate the construction progress of the project, and ensure the physical quality of the project.
    VL  - 10
    IS  - 4
    ER  - 

    Copy | Download

Author Information
  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • College of Civil Engineering, Guangzhou University, Guangzhou, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • BGI Genomics Co., Ltd, Shenzhen, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • China Construction Fifth Engineering Bureau the Third Construction Co., Ltd., Changsha, China

  • Sections