Low profit margin is a common issue for construction companies globally, especially for Chinese contractors. In this study, we aim to reduce the project direct cost using the procurement model to enable the contractors to increase their profit at the project level in China. The traditional procurement method used by Chinese contractors is to divide the project direct cost into several big packages, such as civil, structure, structural steel, curtain wall, mechanical, electrical, and plumbing, thus giving away the profit to the subcontractors. However, in North America, contractors use the trade packages and purchase major materials and facility equipment directly as per the specifications, and thus have more control over the project and markup of materials and equipment. In this study, we start with the supply chain model, analyze the western procurement practice, and propose an EPC procurement mode. The proposed model categorizes packages into five groups according to the different characteristics of the procured content, provides different contract templates, utilizes the appropriate contract, provides opportunity for negotiating with suppliers, and manages the interface carefully to reduce the project direct cost, thereby enabling the contractor to increase the profit margin to make the contractor more competitive in the market. The model was further presented and verified using a case study for Chinese contractors by utilizing the procurement model, so that the contractor can reduce the direct cost.
Published in | Science Discovery (Volume 10, Issue 5) |
DOI | 10.11648/j.sd.20221005.15 |
Page(s) | 306-313 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2022. Published by Science Publishing Group |
Traditional Subcontractor Strategy, Trade Packages, Contract Template, Negotiation
[1] | 谭忠杰. 设计单位转型工程总承包业务的思考[J].建筑经济, 2021, 42 (7): 11-14. |
[2] | 曹吉鸣. 工程施工管理学[M]. 中国建筑工业出版社, 2010. |
[3] | 陈宏伟. 后工业化时代建筑企业发展战略研究[J]. 建筑经济, 2021, 42 (7): 5-10. |
[4] | 周静瑜等. 主题乐园设计实务[M]. 同济大学出版社, 2019. |
[5] | R Cigolini, et al. “Supply claim management in construction and engineer – to - order industries”. October 2020. Production Planning and Control. DOI: 10.1080/09537287.2020.1837981. |
[6] | Anand Nair, etal. “Strategic purchasing participation, supplier selection, supplier evaluation and purchasing performance”, 2015, International Journal of Production Research. http://doi.org/10.1080/00207543.2015.1049783. |
[7] | Lan Zhang; Hao Hu and Aiguo Huang. “A Cost Control Model for a Medical Facility in China” AACE INTERNATIONAL TECHNICAL PAPER, 2021, CSC-3683. |
[8] | FIDIC Client/Consultant Model Service Agreement (white book), 1998. |
[9] | FIDIC, Short Form of Contract (green book), 1999. |
[10] | FIDIC, Conditions of Contract for EPC Turnkey Projects (silver book), 2002. |
[11] | FIDIC, Conditions of Contract for Plant and Design Build (yellow book), 2002. |
[12] | FIDIC, Conditions of Contract for Construction (red book), 1999. |
[13] | 电子工业洁净室厂房设计规范 GB50472-2008. |
[14] | ASCE (American Society of Civil Engineers), Minimum design loads for building and other structure, P7-10, 2010, Virginia, ASCE. |
[15] | 集成电路封装测试厂设计规范 GB51122-2015. |
APA Style
Lan Zhang, Hao Hu, Jian Chen, Aiguo Huang. (2022). EPC Procurement Model in China to Reduce the Project Direct Cost. Science Discovery, 10(5), 306-313. https://doi.org/10.11648/j.sd.20221005.15
ACS Style
Lan Zhang; Hao Hu; Jian Chen; Aiguo Huang. EPC Procurement Model in China to Reduce the Project Direct Cost. Sci. Discov. 2022, 10(5), 306-313. doi: 10.11648/j.sd.20221005.15
@article{10.11648/j.sd.20221005.15, author = {Lan Zhang and Hao Hu and Jian Chen and Aiguo Huang}, title = {EPC Procurement Model in China to Reduce the Project Direct Cost}, journal = {Science Discovery}, volume = {10}, number = {5}, pages = {306-313}, doi = {10.11648/j.sd.20221005.15}, url = {https://doi.org/10.11648/j.sd.20221005.15}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.sd.20221005.15}, abstract = {Low profit margin is a common issue for construction companies globally, especially for Chinese contractors. In this study, we aim to reduce the project direct cost using the procurement model to enable the contractors to increase their profit at the project level in China. The traditional procurement method used by Chinese contractors is to divide the project direct cost into several big packages, such as civil, structure, structural steel, curtain wall, mechanical, electrical, and plumbing, thus giving away the profit to the subcontractors. However, in North America, contractors use the trade packages and purchase major materials and facility equipment directly as per the specifications, and thus have more control over the project and markup of materials and equipment. In this study, we start with the supply chain model, analyze the western procurement practice, and propose an EPC procurement mode. The proposed model categorizes packages into five groups according to the different characteristics of the procured content, provides different contract templates, utilizes the appropriate contract, provides opportunity for negotiating with suppliers, and manages the interface carefully to reduce the project direct cost, thereby enabling the contractor to increase the profit margin to make the contractor more competitive in the market. The model was further presented and verified using a case study for Chinese contractors by utilizing the procurement model, so that the contractor can reduce the direct cost.}, year = {2022} }
TY - JOUR T1 - EPC Procurement Model in China to Reduce the Project Direct Cost AU - Lan Zhang AU - Hao Hu AU - Jian Chen AU - Aiguo Huang Y1 - 2022/10/11 PY - 2022 N1 - https://doi.org/10.11648/j.sd.20221005.15 DO - 10.11648/j.sd.20221005.15 T2 - Science Discovery JF - Science Discovery JO - Science Discovery SP - 306 EP - 313 PB - Science Publishing Group SN - 2331-0650 UR - https://doi.org/10.11648/j.sd.20221005.15 AB - Low profit margin is a common issue for construction companies globally, especially for Chinese contractors. In this study, we aim to reduce the project direct cost using the procurement model to enable the contractors to increase their profit at the project level in China. The traditional procurement method used by Chinese contractors is to divide the project direct cost into several big packages, such as civil, structure, structural steel, curtain wall, mechanical, electrical, and plumbing, thus giving away the profit to the subcontractors. However, in North America, contractors use the trade packages and purchase major materials and facility equipment directly as per the specifications, and thus have more control over the project and markup of materials and equipment. In this study, we start with the supply chain model, analyze the western procurement practice, and propose an EPC procurement mode. The proposed model categorizes packages into five groups according to the different characteristics of the procured content, provides different contract templates, utilizes the appropriate contract, provides opportunity for negotiating with suppliers, and manages the interface carefully to reduce the project direct cost, thereby enabling the contractor to increase the profit margin to make the contractor more competitive in the market. The model was further presented and verified using a case study for Chinese contractors by utilizing the procurement model, so that the contractor can reduce the direct cost. VL - 10 IS - 5 ER -